Cladding Remediation Architects
We help building owners, freeholders, managing agents and residents’ management companies put right issues that affect the safety, performance and value of a building, from cladding and façades to fire safety and structural defects.
As architects with a specialism in façade design, we understand how external walls are built, why they fail and how to fix them properly. We act as architect and lead designer, prepare applications to the Building Safety Regulator, and administer the building contract through to completion. We have also prepared cladding remediation grant submissions.
Most cladding projects on existing blocks of flats start with a fire risk appraisal of the external walls (FRAEW) carried out under PAS 9980. It rates the risk as low, tolerable, medium or high.
A medium or high rating does not automatically mean stripping the whole wall. We test options against the outcome the building needs to reach, so the works deal with the risk where it matters and the cost stays proportionate. Read our guide: PAS 9980 explained.
For higher-risk buildings (at least 18 metres or seven storeys, with at least two homes), remediation needs building control approval from the Building Safety Regulator before work starts (Gateway 2), and a completion certificate at the end (Gateway 3).
We prepare and manage both applications, including the design information, the construction control plan and the golden thread of information, so approval is built into the programme from the start.
City Reach is an eight-storey residential building on Buckle Street and Leman Street in Aldgate. We replaced its combustible cladding, insulation and timber balcony decking with a non-combustible A2-rated rainscreen and aluminium decking, with new cavity barriers and fire-stopping, while residents stayed in their homes.
Studio Anyo is architect and lead designer, BSR applicant and contract administrator. Read the City Reach project update.
Not always. If the FRAEW shows the risk can be brought to a tolerable level by replacing some materials or adding measures such as cavity barriers and fire-stopping, full replacement may not be needed.
A building is higher-risk if it is at least 18 metres or seven storeys tall and has at least two homes. If so, remediation works need Building Safety Regulator approval before they start.
Government schemes, such as the Cladding Safety Scheme, may cover eligible costs. We can help you check eligibility and prepare the technical information for an application.
If you own or manage a building with a cladding or fire safety issue, send us your FRAEW or fire risk assessment. We will review it free of charge and tell you the likely options and next steps.